Attention: All prospective bidders for the project
BID REFERENCE NO. ATI6-PB2023-002:
Construction of One (1) Housing Facility for Swine Artificial Insemination sa Barangay (SWAIB) Project at San Remigio, Antique (ABC ₱ 2,500,000.00.00)
- Please be informed of the following:
No. |
Query/Concerns |
Clarifications |
1. |
Payment for Bid Documents |
Payment of Bidding Documents may be done via cash paid directly to our cashier before the deadline of the submission of Bids on October 23, 2023, 9:00 AM. The bidder shall present its proof of payment to the BAC Secretariat on or before the deadline of submission of bid or may send a copy thru the email ati6.bac@gmail.com.
|
2. |
Single Largest Completed Contract |
As per Section 23.4.2.4 of the 2016 Revised Implementing Rules and Regulations: “The bidder must have completed an SLCC that is similar to the contract to be bid, and whose value, adjusted to current prices using the PSA consumer price indices, must be at least fifty percent (50%) of the ABC to be bid: Provided, however, that contractors under Small A and Small B categories without similar experience on the contract to be bid may be allowed to bid if the cost of such contract is not more than the Allowable Range of Contract Cost (ARCC) of their registration based on the guidelines as prescribed by the PCAB.”
Whereas, according to Section 4.3 IAC Categorization of Contractors of the Revised Guidelines for Registration and Classifications of Contractors, the Allowable Range of Contract Cost (ARCC) for contractors under Small A is less than or equal to ₱ 3.0 Million. |
3. |
Permits and clearances |
All expenses relating to the securing of Permits and clearances shall be borne by the recipient. |
4. |
Discrepancies between the Bill of Quantities (BOQ) and Drawings |
|
|
Revision of Annex C - Bill of Quantities* |
|
|
Included in Masonry Works |
|
|
Shall be borne by the recipient |
|
|
Revision of page 5 of Annex B – Drawings |
|
*Total revision of Annex C - Bill of Quantities in order to synchronize with Annex B -Drawings |
||
5. |
What are the required Site Investigation Reports |
Affidavit of Site Inspection |
6. |
Where to include/reflect the discount offered by the bidder in the financial document? |
Discounts offered shall be indicated in letter “d” of the Bid Form. The template shall be attached together with this document. |
- The following documents are attached to this document:
- Bid Form for the Procurement of Infrastructure Projects
- Bid Securing Declaration Form
- Omnibus Sworn Statement (Revised)
- Revised Annex A – Program of Works
- Revised Page 5 of Annex B – Drawings
- Revised Annex C - Bill of Quantities (all pages)
- Other Concerns:
- The Eligibility, Technical, and Financial Proposals must be properly tabbed for easy reference and must be submitted in sequence/order per Checklist of Requirements.
- The BAC shall no longer entertain any question/request for clarification after the issuance of this Bid Bulletin.
- All revised and required documents as indicated/instructed in this document shall be followed and will serve as basis for checking as to compliance of the Bidders during the Opening of Bids.
For the guidance and information of all concerned.